Parts have started to arrive and I have been busy assembling. The one big piece I'm missing (because it is out of stock) is my mash tun from SSBrewTech. Im hoping it comes in this week. I was able to put most of the rest of this together.
I was able to run some leak tests which showed a few things that needed correcting. I also ran a few tests on the boil kettle. Looks like I should be able to expect a 3 degree rise per minute on a 12 gallon boil which seems pretty good. I did have to change the design a bit as I found out that my chiller restricts the flow too much to get an effective whirlpool. So I modified the design to have the whirlpool branch off before the chiller (instead of after). Im a little worried that that will mean any cold break material will end up in the fermenter but I think that will be a try it out and see if that is a problem I need to fix down the road